negative cost

1 reply [Last post]
ayman eleish
User offline. Last seen 15 years 47 weeks ago. Offline
Joined: 22 Sep 2005
Posts: 20
Groups: None
Hi all
Is there a way to inter -ve value for unit price or for budget to use it in retention in p3 to creat a payment.
thanks

Replies

Gordon Blair
User offline. Last seen 6 years 35 weeks ago. Offline
Joined: 29 Jul 2005
Posts: 166
Groups: None
Ayman,

Probably wiser to have a separate item for the retention payment.

i.e.

Total Price = £100000

Activity A Budgeted Cost £85000
Retention Payment £15000

HTH,

Gordon