Project Group & Targets

3 replies [Last post]
John Impraim
User offline. Last seen 12 years 41 weeks ago. Offline
Joined: 13 Jul 2001
Posts: 14
Groups: None
Hi Guys,

I have 2 stand alone projects (with targets) which have been made sub-projects to a new project group. Now, how do I display their Targets at the project group level ?

Any help out there ?

John

Replies

Sukumaran Subaram...
User offline. Last seen 9 years 15 weeks ago. Offline
Joined: 2 Mar 2005
Posts: 229
Groups: GPC Malaysia
Make a copy of new project group (eg.PG01) and rename it (eg.PG02). The subproject will be copied together. Set PG01 as a baseline (target) schedule and PG02 as current working file. Go to Tools > Project Utilities > Targets and set PG01 as a target file for PG02.

Regards.
Philip Jonker
User offline. Last seen 15 years 48 weeks ago. Offline
Joined: 7 Nov 2004
Posts: 852
Groups: None
Hi john,

If you have the two target projects, combine them in the same way you did with the updated projects, in a multi project file, and add the same sub-project id’s, and use this group as your new target.
Steven Oliver
User offline. Last seen 11 years 50 weeks ago. Offline
Joined: 8 Nov 2002
Posts: 313
Groups: None
You would have to prefix the activity id’s in your target plan with the same prefix you used to create your sub-projects.

This can be done with a Global Change (Actid = xx&actid), though depending on how your activity id is made up you may need to use the ltrim or left/right text functions.


HTH