Installed Quantity for physical % complete

A
Anand Kulkarni 👤 Member for 21 years 3 months

Dear Wan,



Yes Planned quantities are the budgeted quantities only.



Yes the report gives you resource wise break-up for all the activities with the summary of resources.



Multiples resoures to one activitiy is not an issue at all.





cheers



anand

D
Dylan Wan, PMP EVP 👤 Member for 21 years 4 months

Thanks for your reply, Anand.



Is the planned quantity entered as budgeted quantity in the resource window?



Can I have an activity level quantity? We have multiple resources assigned to the same activity.

A
Anand Kulkarni 👤 Member for 21 years 3 months

Hi Wan,



In Tools/Tabular Reports/Resource/Earned Value



The out put is detailed Resource wise % complete Actual Qty. of Work Performed (ACP), Budgeted qty. of Work Scheduled (BCWP), Budgeted qty. of work scheduled(BCWS, Variance & At completion quantities



cheers,



Anand

Featured Partner

Top Posters

Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts
Jeamiell Ostrovsky
2 posts
Hamzah Ahmed
0 posts
Quinton van Eeden
3 posts
Sunchana Johnston
12 posts
Akram Hammam Mohamed
17 posts
Sagar Raut
14 posts
Patricio_aoa
0 posts