engineer planner /scheduler / Quantity Surveyor, Shibh Al Jazirah Contracting Company, Construction of North West Leg Project,Project Description: An all-new 13 Km. Multilane Dual Carriageway with Service Roads complete with Drainage System, Lighting, Tra

START Date: 
July, 2008
END Date: 
December, 2008

Quantity Surveyors( July  2008-Dec. 2008)

  • Estimate all the quantity needed for As-Built.
  • Prepare Shop drawings using Auto Cad.
  • Prepare Bill of Quantities in excel format.
  • To coordinate with the Consultants to discuss matters regarding the execution and updates of the Project;
  • Prepare bar bending schedules for all the structures concerning Bridges.
  • Prepare setting out data and other survey details of the structures.
  • Prepares quantity calculations for monthly billing certificates.
Experience Hours (Planning & Scheduling): 
1000
Experience Hours (Cost Management): 
1000