Week Starts

1 reply [Last post]
Zhao Huang
User offline. Last seen 5 years 9 weeks ago. Offline
Joined: 19 Dec 2003
Posts: 8
Hi Planner,

Weekly report cut off date should be change from monday to thursday. Plan had been developed, how to change the week starts day?

Thank you!

Jonathan

Replies

Andrew Podolny
User offline. Last seen 1 year 12 weeks ago. Offline
Joined: 16 Nov 2004
Posts: 130
Data-->Calendars-->Global Calendar-->Standard-->Week starts on