Wrong EF date

5 replies [Last post]
Ahamed Shabeer
User offline. Last seen 9 years 48 weeks ago. Offline
Joined: 3 Mar 2005
Posts: 6
Groups: None
I am using p3.1. when I scheduled the project for March 1, some of the activities are giving EF as february. Recently I have upgraded the system to XP SP2. But once I experienced the same problem with 98 SE also.

Please help.

Replies

Ahamed Shabeer
User offline. Last seen 9 years 48 weeks ago. Offline
Joined: 3 Mar 2005
Posts: 6
Groups: None
I don’t have a constraint and milestone. But when I copied the whole program and worked in another system it works perfectly, but with february 1 as data date instead of March 1 which was set in my first PC
Philip Jonker
User offline. Last seen 15 years 48 weeks ago. Offline
Joined: 7 Nov 2004
Posts: 852
Groups: None
Hi Jaco,
I was of for a while bit of a meduical problem, not serious.

What I am thinking is what you are saying, otherwise with milestones that are not correcrly set, you sometimes get this problem. Another one is Sundaram’s suggestion that the problem might be a sub-project that has an earlier data date.
I had a problem the first time I ran P3 under Windows XP, but it was not this problem. I know there is a patch for XP.


Regards,

Philip.
Jaco Stadler
User offline. Last seen 18 years 2 weeks ago. Offline
Joined: 8 Sep 2004
Posts: 299
Groups: None
What is your late dates.
What is the TF. (Negative)
As Philip has adviced this probable mean you have a constraint what your logic is pushing but due to the constraint it has to take up the time some how remember it is only a program

Hi Philip welcome back long time.

Cheers
Sundaram Arunan
User offline. Last seen 18 years 8 weeks ago. Offline
Joined: 25 Aug 2003
Posts: 7
I have checked in one of my schedule which gives correct result.

For your problem i think it may be due to any other subproject id which might have been linked with this current project schedule

Philip Jonker
User offline. Last seen 15 years 48 weeks ago. Offline
Joined: 7 Nov 2004
Posts: 852
Groups: None
Do you have any constraint on these activities? Are they Milestones?