Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Link Tracking

5 replies [Last post]
Vishwas Bindigana...
User offline. Last seen 49 weeks 5 days ago. Offline
Joined: 24 Apr 2004
Posts: 97
Groups: None
Hi Planners,

What are the effects of making changes in the links of activities of the Updated Programmes? Is this contractually allowed and ethical though not stated explicitly in the Conditions of the Contract?

Is there any software available in the market which determines and highlights the changes made in the links of activities in the Update Programmes in comparision to the Baseline Programme.

Replies

David Moses
User offline. Last seen 12 years 15 weeks ago. Offline
Joined: 20 Oct 2004
Posts: 122
Hi there;

If you are monitoring a project with a P3 schedule which was submitted to client and got approval.You are not allowed to change any of the activities Predecessor / Successor links..If you think that it is required then you have to inform the client.This is what I think.

On the other hand; you can compare or follow any of the schedule by Primaplan software...

http://www.primaplan.nl/.

You could download and test the evaluation copy...

I remain
Dayanidhi Dhandapany
User offline. Last seen 3 years 47 weeks ago. Offline
Joined: 18 Mar 2003
Posts: 470
Groups: None
Hi Vishwas,

As long as the contractual completion dates are not affected, the change of links could be allowed in the schedule update or else updating of programme would be meaningless if you want to maintain or simply follow the logic/links as detailed in the aproved baseline schedule for your monthly/weekly schedule update would sometimes give misleading completion dates. But proper documentation of changing links etc., could be found useful at later stage i.e., if you experience any delay in contractual completion dates you can submit the updated schedule if appropriate, to get approval and after the approval that schedule can be used as revised baseline program.

In the market some software programmes are available like SA Pro, Claim Digger etc, for tracking the changes in the activities................

HTH
MK TSE
User offline. Last seen 4 years 37 weeks ago. Offline
Joined: 27 Feb 2002
Posts: 550
Groups: None
For the first question, if you want to project the completion dates without any change in planned working sequence, change any link is not required.
If only comparing the as-built with the planned, change in link is not required (I think).
However, if you want to do some forecast based on what been happened and experience, activity may be re-sequence before scheduling.

there is some off-shelf products available in market, like Claim Digger, etc (There are some discussions in other posts)
Jaco Stadler
User offline. Last seen 18 years 18 weeks ago. Offline
Joined: 8 Sep 2004
Posts: 299
Groups: None
The software that I use to compare logic is P3.

Contractualy you will need to resubmit your schedule to the client for approval highligting the changes and get him to agree it.

Well Maybe Stuart have other views.
Ronald Winter
User offline. Last seen 3 years 49 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None
This has been addressed earlier. Try http://www.planningplanet.com/forum/forum_post.asp?fid=1&Cat=2&Top=6665 for two possable solutions.