Lead planner / Planning Manager, NR Sistems Sdn Bhd, Electrified Double Track Project between Ipoh and Padang Besar
START Date:
April, 2008
END Date:
October, 2008
- Seconded to MMC-Gamuda J.V (Employer Representative) to establish fully integrated design and Construction program for System Works and liaise with Systems Main Contractors on interface key dates with lists of requirements
- Assist Planning Manager to establish and implement project controls for Systems Works Contract
- Coordinate with civil planners and produced a fully integration programme with Primavera P6
- Established baseline works program for Systems and review with the Project Manager and the Systems Contractors if any anomalies