Forum Guest
User offline. Last seen 10 weeks 10 hours ago. Offline
Joined: 28 Jan 2009
Posts: 2
Groups: None
I am surprised to see that after so many years of the first launching of P3 for Windows, the same DOS Tabular & Graphics Reports are still there with no improvement and with no possibility of adjusting the fonts or the graphics.

Does anybody has a way to improve on these reports to have look more professional?

Thanks.

Replies

Forum Guest
User offline. Last seen 10 weeks 10 hours ago. Offline
Joined: 28 Jan 2009
Posts: 2
Groups: None
Thanks a lot Mr. Bhuvanesh

from
arunan
Forum Guest
User offline. Last seen 10 weeks 10 hours ago. Offline
Joined: 28 Jan 2009
Posts: 2
Groups: None
Thanks a lot Mr. Bhuvanesh

Bhuvaneswaran Vel...
User offline. Last seen 6 years 19 weeks ago. Offline
Joined: 28 May 2003
Posts: 19
Groups: None
Dear Sundaram.,

May be the following will help.

***********************
IN P3 do the following:
***********************

Step 1) Export -> Export Data File - Lotus - Resource Data

Step 2) Contents -> Select Activity ID, Resource , Budgetted quantity

Step 3) Format -> Sort by Activity ID

Step 4) Click RUN & OK

***********************
Now Open X-L :
***********************
Step1) Open the X-L file (By default it will be in P3OUT Directory)

Step2) If you didn’t assigned any resources for an Avtivity => Type the Resource and Budgetted qty in the respective fields in X-L.

Step3) To add MULTIPLE resources, copy & paste the Activity ID and do the step 2 above.

Step 4) Save (Note to keep the existing format, don’t convert to X-L)

***********************
Once again IN P3 do the following :
***********************

Step 1) Import -> Import This Period Resource and Cost Data

Step 2) check the path

Step 3) Click Run & OK

Regards.,

Zq qz
User offline. Last seen 12 years 37 weeks ago. Offline
Joined: 6 Jun 2003
Posts: 163
Groups: None
Yes agree with ANIL, b coz in planning you need to analyze don’t 100% rely on computer output / results. Doing the work by hearth is the best you can do for everything.
Anil Gupta
User offline. Last seen 16 years 30 weeks ago. Offline
Joined: 18 Aug 2003
Posts: 27
Groups: None
Dear Sundram
Nothing can be achieved in single stroke .Abt resource loading go through extensive discussion held under topic resource laoding
Sundaram Arunan
User offline. Last seen 18 years 3 weeks ago. Offline
Joined: 25 Aug 2003
Posts: 7
Dear bhuvanesh,

can you please give me a little bit guide to do import/export from excel since i need to feed various resources to some of the activities in my sch. by using a single stroke.

Thanks
MK TSE
User offline. Last seen 4 years 17 weeks ago. Offline
Joined: 27 Feb 2002
Posts: 550
Groups: None
The core design of P3 is no change from DOS to Window version, ie no significant change from v1.0 to 3.1, only new features added.

If you want something excited, I was told on P3e/c. I mayself not prove it yet.
Bhuvaneswaran Vel...
User offline. Last seen 6 years 19 weeks ago. Offline
Joined: 28 May 2003
Posts: 19
Groups: None
Dear,
One of the advantage of GUI compared to DOS is the export/import function. If you are conversant with export import function, you can play in excel the reports in whatever fashion you need.
P3 I feel is Embedded with this feature. Hence make use of it.
Regds.,,