Logic of completed activities

2 replies [Last post]
Joe Mansour
User offline. Last seen 3 years 39 weeks ago. Offline
Joined: 10 Sep 2002
Posts: 46
Groups: None
After completing the schedule and its successive updates until the project completion, is there a way to get a report about the validity of the original logic of the schedule? In other words, suppose we have to redo the schedule for the same project, how can we get a report from the completed project about the corrections we should make for the new schedule?
Appreciate your replies.

Joe

Replies

Gilbert Rayco
User offline. Last seen 37 weeks 5 days ago. Offline
Joined: 24 Feb 2003
Posts: 20
Dear Joe,

P3 can provide u a successor report by:
- Tool, project utilities,export
- choose EX-12, modify per ur requirement
above is effective only if u have maintained a good
records/corrections which are reflected in the as-built planned. otherwise it will not be of help, it can be done but it will be tedious process.

Hope this can assist u


G. Rayco
MK TSE
User offline. Last seen 4 years 25 weeks ago. Offline
Joined: 27 Feb 2002
Posts: 550
Groups: None
In P3, the linkages of a activity are maintained and not deleted even it is completed.
Prepare a prec and succ text report or Export the succ report will have the data