Driven Predecessors List

10 replies [Last post]
Ali Vessali
User offline. Last seen 7 years 9 weeks ago. Offline
Joined: 16 Sep 2001
Posts: 55
Dear P3 users;

I want to create a list of driven predecessors only. As you know in Predecessor field, P3 will list all Predecessors of each activity sorted by Act. ID, but I’m looking for a way to list just driven ones or at least show driven ones first then non-driven.
Anybody has experience or tips?

Thanks,
Ali Vessali

Replies

Jorge Taguinod
User offline. Last seen 2 years 36 weeks ago. Offline
Joined: 8 Jul 2003
Posts: 139
Hi Ali!

Based on your post, I agree with Nihats solution. If this is not acceptable to you, can you please explain why you need to get this so I can understand and perhaps provide another option.

Best regards,

Jorge P3 Taguinod
Crown Systems
Syed Ali Hasan
User offline. Last seen 8 years 25 weeks ago. Offline
Joined: 20 Apr 2003
Posts: 10
Groups: None
Hi,

Most of the EXCEL file macros are supplied by Primavera Systems, Inc in the P3 3.0, P3 3.1 in the SUPPORT/UTILS/EXCEL folder in the CD. There are also other useful utilities in the Support folder of the CD. You can also download the latest EXCEL macros from Primaveras Knowledgebase on Primaveras web site.

Best wishes,

Syed Hasan
Primaveras PAR in the Middle East.
Puneet Arora
User offline. Last seen 14 years 38 weeks ago. Offline
Joined: 4 Mar 2002
Posts: 4
Groups: None
Khaled, you can save a lot of planners of misery. Can U mail the file to me please.

Puneet
puneet.arora@eil.co.in
Nishikant Choudhary
User offline. Last seen 20 years 21 weeks ago. Offline
Joined: 8 Nov 2002
Posts: 25
Groups: None
Khalid , can u please share the excel macro with me , cos i think thats the best way , even i would like to test my relationships and logic in @ 4000 activities that i have to go through to ensure its veracity,please.


Thanks and best regards,
Nishikant
Ali Vessali
User offline. Last seen 7 years 9 weeks ago. Offline
Joined: 16 Sep 2001
Posts: 55
Nihat;

Thanks, I will try that way.

Ali Vessali
Ali Vessali
User offline. Last seen 7 years 9 weeks ago. Offline
Joined: 16 Sep 2001
Posts: 55
Khalid;
I think you are talking about RA application. But, anyhow would you please send your file to this address: avessali@yahoo.com

Thanks,
Ali Vessali
Nihat Yildirim
User offline. Last seen 2 years 16 weeks ago. Offline
Joined: 23 Nov 2001
Posts: 10
Groups: None
Trace Logic might be configured so that it just displays driving activities. This is helpful.
Forum Guest
User offline. Last seen 4 weeks 3 days ago. Offline
Joined: 28 Jan 2009
Posts: 2
Groups: None
Dear Ali


There is an excel file contains macro, you can get predeccessor through this file contains predeccessor and column contains driving relation if it drifing (True) or if it is not driving (false) so you can make a filter in Excel to delete (False) and you will find only driving relationship send me your email to send you the file

my email
kh_abdelaal@hotmail.com


Khalid Abdelaal
Ali Vessali
User offline. Last seen 7 years 9 weeks ago. Offline
Joined: 16 Sep 2001
Posts: 55
Thanx Khalid,

But you know the result of that report. Actually Im working on a detailed schedule with more than 5,000 activities. In such schedule there are several predecessors and/or successors for more activities. So, I want to create a report to show just Driven links to trace the logic easier.
Any other suggestions?

Thanks,
Ali Vessali
Khalid Abdelaal
User offline. Last seen 6 years 21 weeks ago. Offline
Joined: 10 Jan 2001
Posts: 15
Groups: None
Dear Ali Alsalamo Alikom

you can creat this list in tabular report (Tools-tabular report- Schedule)and from content window chose detailed predecessor.
this report contains all predeccesor and signifies driving relation by astric *


rega

Khalid Abdelaal