Negative Total Float

8 replies [Last post]
Bruce Mercer
User offline. Last seen 22 years 4 weeks ago. Offline
Joined: 20 Nov 2001
Posts: 6
Groups: None
I have a project schedule in which I cannot remove the negative float. I have reviewed all relationships and find nothing out of place. I have changed all hammocks to tasks and removed all the constraints except the "Start On" constraint in an effort to eliminate the negative total float, but nothing changes.

A review of the reference manual has not helped. Is this a case of a blinding flash of the obvious?

Thanks in advance for your assistance.

Replies

Jorge Taguinod
User offline. Last seen 2 years 49 weeks ago. Offline
Joined: 8 Jul 2003
Posts: 139
Could it be that you have subprojects? If so, then you may have different Must Finish By dates and different Data Dates.

Check out: Tools, Schedule, Options, Advanced Tab, Project Group Scheduling as this also affects how the project is schedule.

Jorge
Crown Systems (Philippines)
Forum Guest
User offline. Last seen 17 weeks 3 days ago. Offline
Joined: 28 Jan 2009
Posts: 2
Groups: None
Its not just the Project Finish Date that might cause a negative total float. An out of order Late Finish constraint imposed on any activity can also cause Negative TF.

When you encounter a negative TF, check for any activity assigned with a Late Constraint - Finish. Removing all of it will remove the -ve TF.

Imron Asran
User offline. Last seen 13 years 36 weeks ago. Offline
Joined: 13 Jun 2002
Posts: 7
Groups: None
Dear all,

I got same problem with Bruce.

I have done all your advice, but I still find the negative total float. Mostly of activities have negative float and Milestone as well. For your information, this schedule was prepared by my friend so that make me difficult to trace it.

What is the problem with the schedule, any body can help me ?

Imron
Leefaisal Razali
User offline. Last seen 5 years 28 weeks ago. Offline
Joined: 13 Mar 2002
Posts: 13
You just need to go to File, project overview and change your must finish by. other i think you have to check on the constraint -good luck
Ali Hamouda
User offline. Last seen 8 years 26 weeks ago. Offline
Joined: 3 Feb 2002
Posts: 109
Groups: None
Bruce,

you must add to an activity to your project,it is name "Project end", or "project completion date"
and make it is type as a "finish milestion"

then , in the overveiw window or p3, you must put the Project must finish = to the "project completion date".

this ensure that you will not have any confusion about the calculated end date and the must finish.
because the calculated end date will be related to the activity "project completion date"

I hope could explain what is in my mind.

regards
Ali

Bruce Mercer
User offline. Last seen 22 years 4 weeks ago. Offline
Joined: 20 Nov 2001
Posts: 6
Groups: None
Ah Hah!...I was right!! It was a blinding flash of the obvious! In Project Overview the must finish date was before the project’s scheduled finish date. Once changed and a review of the schedule printout, all is OK!

Thanks Greg and Mohd for your timely responses.

Warm regards,

Bruce
Mohd Mahd
User offline. Last seen 16 years 44 weeks ago. Offline
Joined: 13 Jul 2001
Posts: 62
Groups: None
one last step, which might help.
in P3 menu, go to Tools then Schedule, then schedule window will open, enable the 3 options, then, ok.
u choose, to print the schedule report. in that report, u should be able to see the accurate cause of the negative float.
regards, mohd
Greg Stacey
User offline. Last seen 6 years 41 weeks ago. Offline
Joined: 19 Jun 2001
Posts: 23
Groups: None
You have covered most things, but what application are you using? Is there any global set-up you have not checked, like project overview in P3, that has a must finish by date.
What about product support?

Sory for lack of answers.