Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Resource levelling up (not down)

2 replies [Last post]
Peter Holroyd
User offline. Last seen 29 min 32 sec ago. Offline
Joined: 6 Jun 2005
Posts: 164
Normaĺly in P6 resource levelling you specify a limit for the critical resource and then P6 adjusts the schedule to avvomodate this limit (never understood on what criteria it moved activities). I was looking to do the opposite - level up. E.g. for instance we have an overall budget spread on our accepted schedule but the client has a greater budget limit in certain periods and wants to spend it as he may lose it. How can I get P6 to adjust the schedule automatically to reach these budget limits?

Replies

david kelly
User is online Online
Joined: 12 Feb 2016
Posts: 38
Groups: None
What I usually do, is break the work down into as many parallel jobs that can be done at the same time as possible. Then allow the levelling to choose "enough" of these jobs to fill the availability, probably by an activity-level priority code.
david kelly
User is online Online
Joined: 12 Feb 2016
Posts: 38
Groups: None
Peter, Tragically, you could get P3 to do this in 1990. But P6 does not "crunch" during resource levelling. The best way to do it is to transfer the data into Spider Project, complete the levelling, and send it back. It is a shame that P6, which is a magnificent piece of late 2oth century software, remains unfinished.