Tasks dates not imported in P6

1 reply [Last post]
rox lra
User offline. Last seen 21 weeks 2 days ago. Offline
Joined: 1 Feb 2018
Posts: 8
Groups: None
Hi all, I am trying to import and MS project file (MPX) to Primavera P6 and after a successful import, the start/finish dates are not imported in P6. If the activity is 100% completed, I only have the A in the start/finish cell in P6. Any thoughts pls?

Replies

david kelly
User offline. Last seen 3 weeks 20 hours ago. Offline
Joined: 12 Feb 2016
Posts: 34
Groups: None

Rox,

 

P6’s main purpose is to calculate start and finish dates.  Specifically Early, remaining early, late, remaining late and planned start and finish. It is a long time since I imported an MPX file, but when importing a spreadsheet you cannot import any of these dates, you can only import dates that are input to the schedule calculations.  To populate date fields in P6 you need to schedule.