Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Contractor controlled schedule items...

1 reply [Last post]
John Reeves
User offline. Last seen 18 weeks 1 day ago. Offline
Joined: 10 May 2013
Posts: 343
Groups: None

I often read about getting backup from contractors for schedule information.  The following varies greatly, but based on a wide swath of the AEC industry contractors largely and commonly do what they want.  A large problem on large projects is getting enough bidders, and between that and needing to work with these same people again - much of the spec requirements is in a gray area.   For example, a contractor turns in a schedule with 5 long lead items with a contratrived duration of say 3 days float.  Close enought to the critical path that any minor set back will set-off a slew of delays.  Does an owner have the right to demand duration quotes from Suppliers?  Are these always in writing?  I have seen such delivers difficult to obtain.  As a scheduler, what commonly happens is the contractor PM or above talks to top brass and such requests go away.  After, 30 years - and working on both sides - I see contractors getting their way more commonly.  One thing that is common is the contractor making changes to the schedule spec in negotiation and it gets approved by people who have no idea if those items matter.

Replies

Zoltan Palffy
User offline. Last seen 21 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

Long lead times can vary during these times of the supply chain shortage. Another factor may be the price that the contract is willing or wants to pay. Maybe paying more can get the long lead item here sooner. But that is his call so the owner is stuck with it. 

I think you see contractors getting their way more commonly because an owner can not dictate means and methods. 

The people who are signing off on the chnages to schedule specificaitons must have the authority to do so and should check with the specfiicaiton writer prior to signing off on the changes to determing if the changes are acceptable.