Price escalation claims, for example from starting NTP 6 months later...

J
John Reeves 👤 Member for 13 years 2 months

Price escalation claims, for example from starting NTP 6 months later... - what does the contractor have to provide?  Do they have to provide both subcontractor's original quotes and revised quotes - or do they have to provide just the current quote or sub-contract?

What should be given to an estimator for an Independent Cost Estimate to ensure the the claim is reasonable - the sub-invoices with quantities but with prices redacted?  

Z
Zoltan Palffy 👤 Member for 17 years

check the specifications sometimes bids are locked in for a specific period of time. But I have not seen at as long as  6 months.

Yes you, your subs and the 3rd tier subs would have to provide back up for escalation

Featured Partner

Top Posters

Ashkan Mohammadi
0 posts
Jeroen De Bauw
0 posts
Senior Planning Engineer
0 posts
Kristian Mcwilliams
1 posts
dagogo dan - jumbo
2 posts
Alex Lyaschenko
27 posts
James Williams
75 posts
xerxes
0 posts
edwin
0 posts
jhalluk69
0 posts