Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Comparing vs the Approved Baseline vs From the previous month and remaining logic.

No replies
John Reeves
User offline. Last seen 2 weeks 4 days ago. Offline
Joined: 10 May 2013
Posts: 343
Groups: None

I am on a project where the remaining logic has the project 20 days behind, but 24 days behind the dates for the same item from the Approved baseline from 8 months prior.  Is the project 20 or 24 days behind?  I would say 20, others say 24.  24 would be more correct for a claim situation, but how often do these really end up in court or arbitration - the 20 is more practical.  In this case its not a big difference - but it can be.  In this case I am guessing calendar complications, but it can be caused by many things.