I think that a better option would be to say revise and resubmit.
Somewhere along the line there if a project falls behind schedule certainly an owner must be made aware of it. How are you going to do that if you do not submit it. I would submit it along witha narrative of why it is behind schedule. Then is it was behind due to the owners fault chnages ect. I would also say in the narrative that I was prepairing a time impact analysis. If it wa smy fault (contractors) then I would say that I was preparing a recovery schedule to get the project back on schedule.
Typically if a schedule a project is on schedule then you can says received for record purposes.
If a schedule is 20 days or more behind scheule then I would say revise and resubmit.
If the project is behind due to the owners actions or inactions then you MUST submit a negative schedule and then give the owner the opportunity to decide what he wants to do.
He has 2 options
option #1 do nothing and let the end date slips and grant a time extension provided that the time impact anlaysis is in order.
option #2 ask the contrator to prepare a recovery schedule along with the associated costs to recover.
you must inform the owner so to give him the opportunity to make one of these decisions.
Member for
16 years 3 monthsI think that a better option
I think that a better option would be to say revise and resubmit.
Somewhere along the line there if a project falls behind schedule certainly an owner must be made aware of it. How are you going to do that if you do not submit it. I would submit it along witha narrative of why it is behind schedule. Then is it was behind due to the owners fault chnages ect. I would also say in the narrative that I was prepairing a time impact analysis. If it wa smy fault (contractors) then I would say that I was preparing a recovery schedule to get the project back on schedule.
Typically if a schedule a project is on schedule then you can says received for record purposes.
If a schedule is 20 days or more behind scheule then I would say revise and resubmit.
If the project is behind due to the owners actions or inactions then you MUST submit a negative schedule and then give the owner the opportunity to decide what he wants to do.
He has 2 options
option #1 do nothing and let the end date slips and grant a time extension provided that the time impact anlaysis is in order.
option #2 ask the contrator to prepare a recovery schedule along with the associated costs to recover.
you must inform the owner so to give him the opportunity to make one of these decisions.