Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

how items are included in a master schedule

3 replies [Last post]
sharjeel faiz
User offline. Last seen 3 years 7 weeks ago. Offline
Joined: 2 Apr 2015
Posts: 4
Groups: None

If the scope of an EPC project consists of 100 items, big and small, how does the planner include it in the master schedule?

thanks

Replies

Rafael Davila
User offline. Last seen 1 week 3 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241

Might also be of interest the following links:

Zoltan Palffy
User offline. Last seen 3 weeks 6 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

on option is to make samller schedules and then when importing select the master schedule and during the importing process select add to existing project instead of creat a new project.

Rodel Marasigan
User offline. Last seen 1 day 20 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699

Hi Sharjeel,

Depending on how the master schedule is setup and what is the company policy and procedures for Master Schedule.

Some company procedure requiring Level 3 for integrated Master Schedule and Level 4 & Level 5 for contractors schedule.

You can code the contractor's level 4 or level 5 to match Master Level 3 schedule for easy update.