How do I build Summary Schedule from details Schedule

3 replies [Last post]
Samuel Rotimi
User offline. Last seen 3 years 1 week ago. Offline
Joined: 16 Feb 2018
Posts: 4
Groups: None
All, Pls I need help on how to build a summary schedule in P6. How do I identify what should be a summary of the program and how do I build it. Thanks.

Replies

Jerome Odeh
User offline. Last seen 5 weeks 2 days ago. Offline
Joined: 19 Jan 2004
Posts: 102

Samuel,

Once you've identified & categorized the major elements of your schedule as advised by Zoltan, you can set up your schedule as shown in this blog post.

https://www.plannersplace.com/blog/my-settings-04-schedule-roll-up-in-microsoft-project-p6

The blog post covers Summary Schedule settings in Microsoft Project & Primavera P6.

=jerome

Zoltan Palffy
User offline. Last seen 16 weeks 6 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

just think of the major elements of work and categorize them.

use the categories to create the wbs structure

then add you activities to that wbs

Zoltan Palffy
User offline. Last seen 16 weeks 6 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

just think of the major elements of work and categorize them.

use the categories to create the wbs structure

then add you activities to that wbs