Activity Layout / Website Timescale Issue

10 replies [Last post]
troon sigma
User offline. Last seen 3 years 6 weeks ago. Offline
Joined: 15 Apr 2020
Posts: 23
Groups: None
Hi, I publish a website or Activity Layout and face a problem.  The timescale in the website or the Activity layout is totally not reflecting my project start and finish dates.   For instance my project start/finish dates are 2018 to 2020, the timescale is showing 2010 - 2011.  And, I am unable to change this timescale in anyway. I have tried changing Timescale from Page Setup but it doesn't help at all. Can anyone help?ThanksRegards

Replies

Zoltan Palffy
User offline. Last seen 20 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

on your setup page set the print options to fit on one page

troon sigma
User offline. Last seen 3 years 6 weeks ago. Offline
Joined: 15 Apr 2020
Posts: 23
Groups: None

Yes, default printer is set up. It is my HP printer. 

Zoltan Palffy
User offline. Last seen 20 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

do you have a default printer setup ?

troon sigma
User offline. Last seen 3 years 6 weeks ago. Offline
Joined: 15 Apr 2020
Posts: 23
Groups: None
I have installed P6 R20 but it has same issue. In fact, changing anything in Page Setup does not have any effect in the website / layout.  Even, if in Page Setup, I select only Gantt Chart, I still see in the website/layout activity table.
troon sigma
User offline. Last seen 3 years 6 weeks ago. Offline
Joined: 15 Apr 2020
Posts: 23
Groups: None
I have installed P6 R20 but it has same issue. In fact, changing anything in Page Setup does not have any effect in the website / layout.  Even, if in Page Setup, I select only Gantt Chart, I still see in the website/layout activity table.
troon sigma
User offline. Last seen 3 years 6 weeks ago. Offline
Joined: 15 Apr 2020
Posts: 23
Groups: None

No, it is P6 PPM.  R 8.3

Zoltan Palffy
User offline. Last seen 20 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

is this p6 Web ?

and what version of P6 are you using

troon sigma
User offline. Last seen 3 years 6 weeks ago. Offline
Joined: 15 Apr 2020
Posts: 23
Groups: None
Thanks Zoltan, but it didn't work. I have tried PS and PF and also I tried custom date.  I changed printer to PDF and also set the size to 17/11 However, the Activity Layout and in the website also, the timescale is not reflecting the real project dates.My project is from Feb-21 to Oct-21 but timescale showing is from 2011 to 2016. Anything else I can check?
troon sigma
User offline. Last seen 3 years 6 weeks ago. Offline
Joined: 15 Apr 2020
Posts: 23
Groups: None
Thanks Zoltan, but it didn't work. I have tried PS and PF and also I tried custom date.  I changed printer to PDF and also set the size to 17/11 However, the Activity Layout and in the website also, the timescale is not reflecting the real project dates.My project is from Feb-21 to Oct-21 but timescale showing is from 2011 to 2016. Anything else I can check?
Zoltan Palffy
User offline. Last seen 20 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

thast very odd in the page setup under options you should be able to set the Timescale Start date (TRY setting that to PS) and you should be able to set Timescael Finish to (PF) Project Finish.

 

also on the page tab make sure that you select Fit timescale to 1 pages wide

and set the page size to 11x17 (make sure your default printer does 11/17 or set it to print ot a pdf printer)