Resource unit of measure

2 replies [Last post]
Mohamed Nizam
User offline. Last seen 3 years 49 weeks ago. Offline
Joined: 18 Feb 2007
Posts: 16
Groups: None
Is any way to material resource as primary resource Second how to assign of unit of measure such as hour for labor and non--labor Third in resource tab of activity details of update primary resource is any setting to automatically update other resource

Replies

Rafael Davila
User offline. Last seen 1 day 12 hours ago. Offline
Joined: 1 Mar 2004
Posts: 5233

Agree, when consumable resources such as raw materials are lacking activities are delayed.

Zoltan Palffy
User offline. Last seen 20 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

Is any way to material resource as primary resource - thats depends on if the # Units of the material is driving the activity

Second how to assign of unit of measure such as hour for labor and non--labor - yes go to the resource and look under the  

details tab and there is a drop down there for unit of measure. If you do not see the one you want you can add it by going to Admin then Admin Categories then Units of measure 

Third in resource tab of activity details of update primary resource is any setting to automatically update other resource

go to Projects and on the Resources tab under Resource Assignments set the settings there