Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Estimating the Resource/Act.

3 replies [Last post]
Ali Hamouda
User offline. Last seen 8 years 26 weeks ago. Offline
Joined: 3 Feb 2002
Posts: 109
Groups: None
Hi, I want to explode this Question so as we can enrich all the members knowledge about Planning. what is the procedure in estimating the Nos of Resources for each Activity? Regards Ali

Replies

Ernesto Puyana
User offline. Last seen 8 years 13 weeks ago. Offline
Joined: 12 Jan 2001
Posts: 111
Groups: None
You have to be careful with production rates units: 2 hours/M3 or 2 M3/hour? In the first case: 500M3*2hours/M3=1000hours Those are crew-hours or man-hours, depending on how the production rate is stated. 1000 crew hours can be acomplished by 1 crew in 1000 hours or by 1000 crews in 1 hour. But there's a phisical and practical limit to the number of crews you can assign to a particular job: the 500M3 pour in question. That's where you need experience and common sense to determine the right number of units (crews) to assign. This logic has it's limits. Somebody once said that if all thing where like this, then you could acomplish an activity called pregnancy assingning 9 women for a month instead of one woman for 9 months.
Ali Hamouda
User offline. Last seen 8 years 26 weeks ago. Offline
Joined: 3 Feb 2002
Posts: 109
Groups: None
Hi, what about the production rates i.e if we have for example the production rate for each M3 of Pouring roof concrete .then if we know how many meter Quibs needed for this Roof, then we will be able to estimate the number of resources that mean if 2 labours can make 1M3 concreting, then if we have 500m3 concrete then the number of Resources needed for the 500M3 will be 2x500=1000 Man needed for this roof and if we are going to construct the roof in 10 days.then we will have 1000/10=100Man/day and this Idea can be generalized for any type of activity. That is why they create Productin Rates Am I right or wrong? Best wishes Ali ---------------------------
Se de Leon
User offline. Last seen 3 years 15 weeks ago. Offline
Joined: 15 May 2001
Posts: 321
Groups: None
I don't think you can estimate the number of resources per activity per se because resources depends largely on the type of activity. Ex. if you want to estimate a concreting activity your resources would be cement, sand, labor, mason etc. but if your activity is getting a construction permit your resources would be the laison officer only who would follow up this permit. When you're talking of construction activities, I advised you to pick some estimating books or for comprehensive use get a copy of RS Means. These references would give you an idea what are the resources needed for a specific activity. Hope this would help.