Hi!
So in order to be able to earn at a higher level WBS for % Complete, I have cost loaded activities at a higher level WBS that are broken down into activities at a lower level. Example - Construction WBS with 4 activities - Piping, Electrical, Civil, Structural. These 4 activities hold the budgets for our interaction with our cost program. However, I created lower level WBS, example, Piping in East Building, Piping in West Building and in those lower level WBS, I have specific activities. I am using Performance % complete in order to use the roll up of the progress to transfer to the progress on the higher level , cost loaded activities.
Problem is that the Performance % Complete is not rolling up on these lower levels.In one of the lower level WBS, I have 4 activities - 3 at 100% complete and 1 at 95% complete but yet the WBS is showing 0%.
Activities at the lower level have a $1 resource attached.
What am I missing?
TIA
Heather
Replies