Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

delay and out of sequence TEST

1 reply [Last post]
Abderrahim OUBDI
User offline. Last seen 4 years 10 weeks ago. Offline
Joined: 19 Jan 2020
Posts: 11

Hello,

I have done a test updating the schedule at a specific data date (last week):

1- Updating without correcting the out of sequence activities----> result: 32 days of delay

2- Updating with correcting the out of sequence -----> result: 10 days of delay.

Question: Do I have the right to make the correction of out of sequence to meet the actual scenario on the site in order to give an accurate data or I should not make any changes in the current schedule.??

Replies

Zoltan Palffy
User offline. Last seen 21 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

You have the right to make the correction of out of sequence work. 

The update should reflect real world conditions. 

Also in your update narrative I would state what I did and why I did it 

If you did not correct it your would be over inflating your dealy.

From an owners perspectivie he gladly embrace the shorter delay.