Accrual Type - you can accrue at the finish of the activity by using this cell.
This you cannot do if using resource curves as the minimum increment is 5%, you need a 0 time event at the end of the activity, not uncommon when dealing with financial resources.
For renewable resources it does not makes sense most of the time. Such allocation makes sense for resource production if using other software but I doubt if using P6 this would ever make sense. If using P6 only makes sense for financial resources and P6 provides for it.
Member for
16 years 3 months
Member for16 years3 months
Submitted by Zoltan Palffy on Fri, 2019-03-22 13:09
Member for
16 years 3 monthscheck both filters critical
check both filters critical AND longest path
or create a new activity code all it my path and give it a code value of CP for critical path
now filter for the last activity in the schedule
now look at the predecessor window make sure that the columns labeled critrical and driving are shown if not add them
now look at the predcessors and look for the one that has BOTH critical and driving boxes checked
now highlight that activity and seelct GOTO at the bottom
keep doing this until you get to the activity that is on the data date or the start of the project
now highlight all of these activites and right click and select Assign
then select Activity Codes and select the code that you just added my path can select the CP value
now add a new filter
where my path equals CP
this is your true driving critical path
Member for
6 years 4 monthsHi Guys, Can you suggest
Hi Guys,
Can you suggest other ways of identifying ''CRITICAL PATH'' other than these 02 options:
1- Total Float Less Than or Equal to (any value xyz)
2- Longest Path
If you have any other ways to identify critical path, so please share.
Member for
6 years 4 monthsHi Zoltan, So the remaining
Hi Zoltan,
So the remaining units will provide me forecast curve?
Member for
16 years 3 monthsyes you can select the
yes you can select the remaining units and generate a curve
Member for
6 years 4 monthsHi Guys,Can you help with 01
Hi Guys,
Can you help with 01 clarification please?
How can we prepare forecast progress s-curve from p6?
Can we use ''Remaining Labor Unit'' from ''activity usage spreadsheet'' in p6 to develop a forecast progress curve?
Member for
21 years 7 monthshttps://www.projectcubicle.co
https://www.projectcubicle.com/assigning-expenses-in-primavera-p6/
Accrual Type - you can accrue at the finish of the activity by using this cell.
Member for
16 years 3 monthsby default the distribution
by default the distribution of the curve is linear however you can assign a curve by going to the resource tab
right click and select Resource Assignmnets Columns
expand the General caterory on the left and select Curve and bring it to the right
not it is available in the resource tab
now click in the box and select your curve distribution