Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

project delay

3 replies [Last post]
djedilat toumi
User offline. Last seen 4 years 28 weeks ago. Offline
Joined: 14 May 2018
Posts: 9

Hello every one, 

how can i calculate the construction delay taking in account that the construction isn't finished yet?

Regards.

Replies

Zoltan Palffy
User offline. Last seen 9 weeks 5 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

you stays will tell you that based on where you should be and where you actually are

Kathy Castle
User offline. Last seen 6 years 10 weeks ago. Offline
Joined: 17 Apr 2018
Posts: 22
Groups: None

Are you asking techniques related with construction delay analysis ? 

Zoltan Palffy
User offline. Last seen 9 weeks 5 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

the delay is when it was originally planned to finish - when it is forecated to finish

original completion date December 15, 2018

current completion date Jnauary 15, 2019

Delay - 31 calendar days