Critical Path

1 reply [Last post]
ind Vid
User offline. Last seen 4 years 36 weeks ago. Offline
Joined: 30 Apr 2016
Posts: 4
Groups: None

Hello Experts,

 

What % of total number of activities in a baseline schedule should ideally be lying on the critical path (TF=0), a number from your extensive experience / best practice would suffice.

 

thank you

 

indra

Replies

Patrick Weaver
User offline. Last seen 2 days 58 min ago. Offline
Joined: 18 Jan 2001
Posts: 379
Groups: None

There is no single answer to this - small schedules (low number of activities) will tend to have more activities on the critical path than large schedules, but my heuristic is around 20% is good, below 20% better and knowing the probability of achieving on-time completion is heading 'south' once the percentage gets above 20% (particularly if there are multiple critical paths). 

For more on this see: https://www.mosaicprojects.com.au/WhitePapers/WP1037_Probability.pdf