Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Ever heard of a Current Control Plan?

1 reply [Last post]
Ryan Stuttard
User offline. Last seen 5 years 6 weeks ago. Offline
Joined: 6 Nov 2011
Posts: 6
Groups: None

Hi,

Quick context - My PM is making me use a 'Current Control Plan' term instead of 'baseline' as the baseline that links to my live schedule. So, original baseline remains untouched, then overlay that with Current Control Plan (can be edited with agreed changes), then overlay with the live schedule which is progressed against the 'CCP'.

In my experience, I have only ever had the baselines, whether its the original or the updated agreed changes baseline.

Current Control Plans to me would be Project Controls, how the whole project is pulled together, maintained and measured.

So my real question is, have I been fed something that is not widely used as standard or is this just something I have not come across in my experience so far, because my experience as a planner was questioned on the spot due to never hearing the term used for baselines before.

 

Thanks for any responses!

Replies

Zoltan Palffy
User offline. Last seen 3 weeks 15 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

I have never heard of it either but companies oftne use different terms for standard things

Tom Boyle
User offline. Last seen 10 weeks 4 days ago. Offline
Joined: 28 Nov 2006
Posts: 304
Groups: None

Though I've never used the term in practice, CCP makes sense to me as the schedule corresponding to the Current Control Estimate.  As of ~5 years ago, the clients using CCE for cost still used "baseline" for schedule.  Maybe they've changed since then.