Planning, Scheduling & Programming Discussion Member for 11 years 4 months Member for 11 years 5 months Submitted by suninaduvath on Thu, 2017-07-20 10:58 Permalink Any one have detailed cinema Any one have detailed cinema construction schedule ? please help the break WBS and activities details Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Mon, 2016-11-21 09:57 Permalink Hi TimothyYes you should Hi Timothy Yes you should place the procurement duration into your programme. I use a sub chart with the procurement tasks starting with release of design details followed by: 1. Tender 2. Workshop drawings 3. Approval 4. Manufacture / Procurement 5. Delivery 6. Stock take / storage These are all linked FS and then linked to the first activity task that needs the materials using an ALAP link. Then if: a. The design is late then the progress on site is delayed. b. If the work is delayed the designer has more time. Best regards Mike Testro Log in or register to post comments
Member for 11 years 4 months Member for 11 years 5 months Submitted by suninaduvath on Thu, 2017-07-20 10:58 Permalink Any one have detailed cinema Any one have detailed cinema construction schedule ? please help the break WBS and activities details
Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Mon, 2016-11-21 09:57 Permalink Hi TimothyYes you should Hi Timothy Yes you should place the procurement duration into your programme. I use a sub chart with the procurement tasks starting with release of design details followed by: 1. Tender 2. Workshop drawings 3. Approval 4. Manufacture / Procurement 5. Delivery 6. Stock take / storage These are all linked FS and then linked to the first activity task that needs the materials using an ALAP link. Then if: a. The design is late then the progress on site is delayed. b. If the work is delayed the designer has more time. Best regards Mike Testro
Member for
11 years 4 monthsAny one have detailed cinema
Any one have detailed cinema construction schedule ?
please help the break WBS and activities details
Member for
19 years 10 monthsHi TimothyYes you should
Hi Timothy
Yes you should place the procurement duration into your programme.
I use a sub chart with the procurement tasks starting with release of design details followed by:
1. Tender
2. Workshop drawings
3. Approval
4. Manufacture / Procurement
5. Delivery
6. Stock take / storage
These are all linked FS and then linked to the first activity task that needs the materials using an ALAP link.
Then if:
a. The design is late then the progress on site is delayed.
b. If the work is delayed the designer has more time.
Best regards
Mike Testro