Lag ,Total Float and Duration

2 replies [Last post]
Arun Vasanth
User offline. Last seen 5 years 42 weeks ago. Offline
Joined: 12 Oct 2009
Posts: 200
Groups: GPC Qatar

Dear Family Members

What is the maximum and minimum Lag allowed in a program??

What is the maximum Activity duration can be allowed in a program??

What is the maximum and total float allowed in a program ??

 

Regards

Arun.V

Replies

Rafael Davila
User offline. Last seen 2 weeks 5 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241

There are no such thing as a universal rules for planning, the rules shall be used only as a guide/warning on possible errors but not to define them as definitive error. Some of these rules might prevent you from creating better models.

Say concrete placing activity takes 6 hours but curing shall start after the 4th hour; there is a necessary lag that is more than 50% the duration of predecessor. You can bypass such 50% requirement if model lag as an activity.


Say an activity takes 3 months, common in linear jobs; if you split the activity into separate activities then resource leveling might spread them apart instead of keeping the activity contiguous.

Float is a calculation, if the software can do the right calculation and the model is good it will be whatever it comes to be.

Kannan CP
User offline. Last seen 23 weeks 6 days ago. Offline
Joined: 12 Jun 2008
Posts: 290
Groups: None

Hi Arun,

1. For SS+ Lag, the lag should not be more than half of  the predecessor duration. Always try to avoid FS+Lag.

2. Try to limit the construction activities in 21 days, to monitor & control it properly.

3. Total Float depends on the proper logic in the programme.

 

BR

Kannan