Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Lag ,Total Float and Duration

2 replies [Last post]
Arun Vasanth
User offline. Last seen 5 years 37 weeks ago. Offline
Joined: 12 Oct 2009
Posts: 200
Groups: GPC Qatar

Dear Family Members

What is the maximum and minimum Lag allowed in a program??

What is the maximum Activity duration can be allowed in a program??

What is the maximum and total float allowed in a program ??

 

Regards

Arun.V

Replies

Rafael Davila
User offline. Last seen 1 week 3 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241

There are no such thing as a universal rules for planning, the rules shall be used only as a guide/warning on possible errors but not to define them as definitive error. Some of these rules might prevent you from creating better models.

Say concrete placing activity takes 6 hours but curing shall start after the 4th hour; there is a necessary lag that is more than 50% the duration of predecessor. You can bypass such 50% requirement if model lag as an activity.


Say an activity takes 3 months, common in linear jobs; if you split the activity into separate activities then resource leveling might spread them apart instead of keeping the activity contiguous.

Float is a calculation, if the software can do the right calculation and the model is good it will be whatever it comes to be.

Kannan CP
User offline. Last seen 19 weeks 14 hours ago. Offline
Joined: 12 Jun 2008
Posts: 290
Groups: None

Hi Arun,

1. For SS+ Lag, the lag should not be more than half of  the predecessor duration. Always try to avoid FS+Lag.

2. Try to limit the construction activities in 21 days, to monitor & control it properly.

3. Total Float depends on the proper logic in the programme.

 

BR

Kannan