Hi guys,
I am working on a large mining project in RSA with the end date towards the end of 2022. The project is not that complex and is driven by mining as these projects typically are. The problem lies in that the master schedule carries 7500 activities and if you add the EPCM and shaft sinker activities you end with +30 000 actvities. This becomes an unmanageable beast that only sucks up planning resources and add very little value to the project.
I am all for detailing the project to the necessary level but the project director and myself agree that we need to find a simpler method to do this. We are running Primavera 6.8.3 with Risk analyser on an online platform where contractors can access their schedules.
Currently these schedules are not linked but are used to manually update the master and this acts as the central point of data capturing and reporting.
I have read all the papers on project levels etc and we have a very good project management system but I need some advice in this regard. At 1st peak the project employed 8 planners with 4 more shared between the contractors. The numnber has come down to 5, this excludes mine planners.
Project is in the region of $2b.
Any ideas and suggestions of what worked on other projects of a large scale and long duration would be highly appreciated.
Morne
Replies