Gents;
Could you please advise me a valid contractual phrase refering FIDIC to protect the skin of myself.
Sceneraio1 : Approved baseline MEP Programme prepared based on floorwide single access.
Scenerio2: Due to tremendous delay in civil works - 209 calendar days as of 9 February 2016 (total duration for MEP installation completion = 217 calendar days). No complete access was given to any floor as per approved baseline.
Scenerio 3 : Civil contractor revised the access dates in zone wise and vertcally scattered manner. Intially 4 access dates changed to 4 zones x 4 access = 16 Access dates.
Scenerio 4: MEP contractor revised the programme; considering the last access is giving to zone 4 where main elecrical riser, electrical rooms and LV room located. Sequencing changed and durations of activities increased.
Question : Shall civil contractor can claim to use the duration of baseline in the revised MEP completion programme? In this moment baseline is valid benchmark to revise programme; since they changed their sequence in providing access for MEP works.
Thanks
Anil
Replies