Regarding S Curve

1 reply [Last post]
Pradeep Kumar
User offline. Last seen 8 years 49 weeks ago. Offline
Joined: 1 Sep 2015
Posts: 4

Hi,

Can someone suggest me, wheather S curved generated from Manpower Loading & S Curve generated from Cost loading be the same.

If I keep the weightage of cost and adjust the manpower based on that cost weighted percentage. Will that be right ????

 

Please advise.

Replies

Zoltan Palffy
User offline. Last seen 21 weeks 5 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

I doubt that they will ever be the same since you would include procurement of equipment as a dollar item not necessarily any direct labor manhours are associated with this.

no you can't do that you might have a piece of equipment that costs 1 million dollars but it only takes 1 day to set it. You cant adjust the manpower based on the piece of that equipment that will not work.