Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

NEC3 How to calculate delay impact in period where no programmes are accepted.

1 reply [Last post]
David Gray
User offline. Last seen 46 weeks 6 days ago. Offline
Joined: 22 May 2008
Posts: 8
Groups: None

I am working on a NEC3 project which has gone several months without having an accepted programme.

What is correct way to assess a compensation event in the period where there is not an accepted programme?

For example the last accepted programme is January and the event occurs at the start of June.  Should progress from the End May rejected programme be added to the January programme to give a more realistic position at the time of the event.  At the moment if the January programme is used the event is overstated.

I guess the question is also; if progress is added to an accepted programme is the programme still accepted? 

Opinion here is divided.  

Any views?

 

 

 

Replies

Rafael Davila
User offline. Last seen 3 weeks 8 hours ago. Offline
Joined: 1 Mar 2004
Posts: 5241

No matter if accepted or not I believe you shall submit for the record the periodic actualization of work performed as well as your TIA's using what you have on hand. Whatever the client does is another issue but keep it on record. Then latter on you might simulate contemporaneous TIA rather than forensic.  If you do not timely put in record your claims you might waive some rights. 

Keep on record you are doing everything that is reasonable, that your submissions are reasonable, if latter on comes out your schedule submission was reasonable as well as your claims it will go in your favor. No schedule is perfect and everyone knows it. 

Schedule Updates are different to Baseline Revisions; Schedule Updates can show a delayed schedule that you can get back in track, when too far then a Revised Baseline is in order.  Unfortunately reaching to an agreement with regard to a revised baseline can be very difficult especially when there are many unresolved delay claims but the schedule actualization on work performed shall not be interrupted by any party.