Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

unit % complete not able to update in Status bar

1 reply [Last post]
Sabaapathy Selvam...
User offline. Last seen 12 weeks 1 day ago. Offline
Joined: 30 Jun 2012
Posts: 10
Groups: None

Hi guys,

I am facing a problem that only for specfic activities i am not able to update any Unit % complete or remaining duration in the status bar.

And also it is showing the critical path in the primavera P6.

The schedule has negative float while submitting to client and it is approved.

Can any one guide how can i resolve the problem ????

Urgent PLzzzzzz

Replies

Zoltan Palffy
User offline. Last seen 16 weeks 1 day ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

need more info

1. Did you look at the TYPE of activity ?

Level of efforts or summary wbs typs of activities are based on the underlaying activities.

2. I would hope that it is showing the critical path in p6 that is what the program is all about hence the name critical ptha method CPM 

3. Why does the schedule have negative float either becasue you are behind schedule or you have not progressed your schedule correctly. 

4. I do not undrstand the title of the post 

unit % complete not able to update in Status bar

you mentioned nothing about units 

have you checked your calculations settings ?

when updating actual units or cost 

subtract actual for at completion

also recalculate actual units and cost when duration % complete changes

and Link actual and actaul this period units and cost