Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Task dependent activity - right or wrong?

1 reply [Last post]
Anthony Obasi
User offline. Last seen 1 year 10 weeks ago. Offline
Joined: 29 May 2015
Posts: 11
Groups: None

Hi everyone,

I am looking at having a discussion or debate in regards to the wisdom of having an activity type that is task dependent. In P6, a Task dependent activity is described as 'an activity that is scheduled according to the activity's calendar rather than the calendar of assigned resources'.

Off all the acitvity types, I find it difficult to understand why an activity is desrcibed as task dependent instead of resource dependent, my reason: I have never come across work or any activity (in a project) that does work automatically or by itself, this still has to be done by resources. So for me, it is simple to say all primary activities should be resource dependent as resoruces determine when an activity starts or finishes.

This would mean having just a project calendar and a resource calenar. The project calendar would then be a standard for all resources and where any resource work time differ signifcantly from the project calendar would then be assigned a resource calendar.

I want to have this discussion and debate in the wider PM community so please do share your thoughts.

Thank you.

 

Anthony

 

 

 

 

 

Replies

Mike Testro
User offline. Last seen 35 weeks 4 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Anthony

I agree with your approach that task calendars and resource calendars should be the same.

If there are special circumstances that require a different calendar then aplly it to both task and resource.

In Asta PowerProject there is a tick box on the resource menu which says - Use Task Calendar.

Best regards

Mike Testro