Hi All,
In one of our projects, we have a situation as follows;
1. Baseline programme submitted and approved as noted.
2. Monthly basis updating is ongoing. It shows some delay because of the delay by client in allocating the site. We sent the EOT claim, but the client is not accepting it.
3. Few months later, client give instruction to reduce some scope as well as to add a few more sope of works. This changed the logic of the schedule and no more useful to compare with the original baseline (for performance measurement)
4.Discussions are ongoing to prepare a revised baseline and how. Is it acceptable to incorporate all the required changes(scope reduction/adding) in the original baseline and submit to client, or incorporate the changes in the current updated schedule (along with the client delays).
Regards
Kannan
Replies