Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

concrete tracking reports

1 reply [Last post]
haytham saad
User offline. Last seen 3 years 13 weeks ago. Offline
Joined: 12 Apr 2013
Posts: 24

I am working in a project contains 3 main concrete buildings A & B & C  each has its total concrete Quantity, i was asked to produce a report showning the excuted Quantities vs  Planned Quantities and showning remaining Quantities, also showning the productivity required to maintain finish date for each building an over come the delay , my question is what should the report contain and if there is any form for these reports, thnxx

Replies

Mike Testro
User offline. Last seen 11 weeks 43 min ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Haytham

Set up a spreadsheet with the dimensions of each concrete component - floors - columns - beams - stairs ect.

This will give you the total m3 of concrete in the project.

Put a date column in the spreadsheet.

Every day collect a copy of the concrete cube test sheets and type the date of the test against the concrete item.

You can then keep a running total of actual concrete production to compare with your planned production rate.

Best regards

Mike Testro