Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

concrete frame rates

1 reply [Last post]
KONESH SRIDARAN
User offline. Last seen 18 years 6 weeks ago. Offline
Joined: 5 Sep 2006
Posts: 7
Groups: None
Hellow Guys,

Working on a concrete frame pre-quaification programme 7 stories. just to get a quick cross check .What is the rate of construction for 1100 (138m X 8m) msq with 38 columns (300 X300m cols) 225mm thick deck.

Thanks

Konesh

Replies

Brij Patwari
User offline. Last seen 17 years 41 weeks ago. Offline
Joined: 28 Aug 2004
Posts: 13
Groups: None
Can any body guide, how to assume resource staturation??
I am working on a project where manpower is not a constraints.. Its about resource saturation??
Can anybody, from their experience tell how can i link Space with 1 man so that i can know how many max no of manpower can be deployed??