Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

How to assign percentege on WBS Level?

1 reply [Last post]
Edmond Marius
User offline. Last seen 7 years 15 weeks ago. Offline
Joined: 13 Apr 2013
Posts: 7
Groups: None

Hi!
I have a project ongoing with no resources assigned. On the construction part I've created an excel spreadsheet with different weights for different equipments installation to show the progress.
I have been asked to compare baseline S-curve with actual S-Curve with the wights from the excel sheet. I need to assign different percentage weights in PV to do that.
Can anyone share some advice?

Replies

Jose Frade
User offline. Last seen 3 years 28 weeks ago. Offline
Joined: 7 Jun 2005
Posts: 144
Groups: None

Hello Marius

 

If you want to compaire the two curves then you need to extract the baseline and fill it with the same relative weights - than have to put back again the baseline.

You can give relative weights at WBS level but to generate a curve from that I am not sure....

 

One option is to use the relative weights you have in Excel and load them in the nonlabor units. Fom this point on is easier. Simply export the nonlabor units to excel (in case you do not have an utility program - Ex: project tracker) and create the graph (Baseline, actual, forecast)

 

Regards

JMFrade