Critical path method - Help ?

1 reply [Last post]
plik plak
User offline. Last seen 11 years 18 weeks ago. Offline
Joined: 19 Dec 2013
Posts: 2
Groups: None

Helo everyvody.

This is my home task:

Activity / Preceding activities

G
M
I
L
B
D
H
K
A
C
F
J
E
-
-
M
M
MI
IM
L
IM
DB
LI
KH
LB
HKA

I need to solve project network diagram. By now i have watched many different youtube tutorials about creating network diagrams. Unfortunately, these "youtube and forum" examples are too simple and my home work is level 99.

Closed circles and dead ends are not allowed:

1906
keelatud.jpg

And this is my best result so far:

1907
3._kodune.png

There are so many opened paths which lead nowhere. Any help would be appreciated.

Replies

Patrick Weaver
User offline. Last seen 4 days 19 hours ago. Offline
Joined: 18 Jan 2001
Posts: 384
Groups: None

The options for calculating the schedule are discussed in detain in: http://www.mosaicprojects.com.au/PDF/Schedule_Calculations.pdf (for both ADM and PDM networks).