Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Approval of Baseline Schedule

3 replies [Last post]
Kaif Mohsin
User offline. Last seen 7 years 14 weeks ago. Offline
Joined: 15 Feb 2011
Posts: 44
Groups: GPC Qatar

Recently, we received comments by the Client's Representative on the submitted 'Baseline Schedule'. One of the comment is to incorporate quantities in Primavera P6 and to provide the same along with production rates in 'Excel' format also.

My question is that is it mandatory to do provide the quantities & the production rates? What's the general practice in this regard, is it necessary to submitt this information all the time along with the Baseline Schedule?

Hoping to have some guidance on this issue from the Senior's out there. Thanks in advance.

Best Regards,

Kaif Mohsin

Replies

Mike Testro
User offline. Last seen 35 weeks 4 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Kaif

You do not have the quantities but you do have the prices.

Resource hours can be extracted from the net price by using a % labour cost divided by the hourly rate.

In this way you have closed the triangle of time / scope / money.

Best regards

Mike Testro

Kaif Mohsin
User offline. Last seen 7 years 14 weeks ago. Offline
Joined: 15 Feb 2011
Posts: 44
Groups: GPC Qatar

Hello Mike,

Nice to hear from you again. I completely agree with you that the CR's request is vaid. Actually, our programme is loaded with 'Manpower Resources' and Cost. For Cost loading, the BOQ Cost was broken down to the required levels & details of the programme and assigned to the activities. 

One of the Contract Clause with respect to "Programme to be Furnished" says: "The programme shall include a histogram indicating the number of workmen and their respective trade and class which the Contractor and Contractor's Sub-Contractors proposed to employ on the site from week to week through the period of the construction of the work."

This what we did, but by bypassing the normal route of calculating manpower required based on quantities to be executed and the production rates. The Manpower resources were allocated to all the activities based on assumptions only, since we didn't have the quantities to work out the manpower required. Now, to be honest we don't have the quantities at all.

So, in this case what should be our response to such a comment from the CR?

Best Regards,

Kaif Mohsin

Mike Testro
User offline. Last seen 35 weeks 4 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Kaif

The C R is usually entitled to request any reasonable information from the contractor.

This request is normal for resource modelling data.

If your programme is not resource modelled and there is no requirement in the contract for it to be so then there is no basis for this data.

However if you get into a claim situation that requires info on low productivity you may regret not giving the data now.

Best regards

Mike Testro