Project resumption after long time of stoppage

4 replies [Last post]
sabry agour
User offline. Last seen 11 years 4 weeks ago. Offline
Joined: 4 Jun 2013
Posts: 5
Groups: None

Dear all

Whats the best way to make project resumption after stoppage for a long time ?

is to add stoppage period as nowork in calender or to make suspend and resume or to add new activites 

is there any advice ??

Replies

sabry agour
User offline. Last seen 11 years 4 weeks ago. Offline
Joined: 4 Jun 2013
Posts: 5
Groups: None

many thanks 

Mike Testro
User offline. Last seen 17 weeks 2 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Sabry

In that case use the calendar.

Best regards

Mike Testro

sabry agour
User offline. Last seen 11 years 4 weeks ago. Offline
Joined: 4 Jun 2013
Posts: 5
Groups: None

yes i know but i want show that in that period work was stoped

Mike Testro
User offline. Last seen 17 weeks 2 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Sabry

Another way is to set a progress data date at the time of restart with the same progress on tasks when stopped or 0% progress for work yet to start.

The calendar method would also work OK.

Best regards

Mike Testro