Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Activity Relationships

1 reply [Last post]
Richard Day
User offline. Last seen 11 years 36 weeks ago. Offline
Joined: 10 Jul 2008
Posts: 11
Groups: None

The contractor has several activities that are tied to its successor with both an fs and ff ties. Activity 1 – 7/08/13 – 7/10/13   Activity 2 - 7/10/13 – 7/12/13. No lags on either relationship. Would this cause the activity to act like it has a fs-1 relationship?

Replies

Mike Testro
User offline. Last seen 36 weeks 1 day ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Richard

What you have is a ladder effect which is common in manufacturing but has no real place in construction.

It should make no difference to the operation of the logic and it could be beneficial when a progress up date goes beyond the SS link.

Best regards

Mike T.