Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Critical vs longest path

3 replies [Last post]
Moutassem Al Kouatli
User offline. Last seen 5 years 19 weeks ago. Offline
Joined: 4 Sep 2007
Posts: 21
Groups: None
Dear planners,

could somone explain to me what the difference between the critical and the longest path (especilly in P3)
can i consider the longest path as a critical path??

cheers

Regards,

Replies

Ronald Winter
User offline. Last seen 3 years 36 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None
I have a paper posted on the web from a PMI College of Scheduling conference concerning this titled, "Longest Path Value." You can assess it at http://ronwinterconsulting.com/published.htm. Perhaps this will make it all clearer. Good luck!
Arnold Puy
User offline. Last seen 9 years 42 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147

CRITICAL PATH – is the longest continuous chain of activities (may be more than one path) which establishes the minimum overall project duration. A slippage or delay in completion of any activity by one time period will extend final completion correspondingly. The critical path by definition has no “float.”

LONGEST PATH (LP) – is the longest continuous path of activities through a project, which controls project early completion. It is possible for otherwise defined critical path activities to not be on the longest path and longest path activities to not show calculated critical float. The longest path analysis is unaffected by activity calendars. The longest path is determined by the string of activities, relationships, and lags that push the project to its latest, early finish date. The longest path is calculated by first performing a CPM ‘forward pass’ to determine driving relationships and the project’s latest, early finish date. The activity (or activities) with the latest, early finish dates are then identified and all predecessor driving relationships traced back to the project start date. These activities constitute the project’s longest path. The longest path depends upon relationships driving the timing of activity starts, thus use of constraints and resource leveling can interrupt and invalidate longest path analysis. Use of interruptible activities can also result in false longest path indications. For complete accuracy, longest path analysis should take place absent of constraints, resource leveling, and/or interruptible activities.
PINAN T.
User offline. Last seen 6 years 22 weeks ago. Offline
Joined: 20 Jul 2007
Posts: 102
critical path relies on tools-->options definition of total float, while longest path contains all the connected activities from the last activity (note: it might end at the middle).. in short, if it contains all the activities from start milestone, then it can be considered as critical path..