Project Progress Percentage in P6

9 replies [Last post]
Qasim Alvi
User offline. Last seen 9 years 15 weeks ago. Offline
Joined: 13 Jan 2012
Posts: 4

I need some assistance about progress percentage in P6.

I want to know that how can compare my baseline (Planned) progress and current progres percentage in P6. I understand the concept of three types of individual activity percentages i.e. Physical, Duration and Units based.

Please Help.

Replies

asd salim
User offline. Last seen 7 years 10 weeks ago. Offline
Joined: 17 Jan 2007
Posts: 6

pls how the total progress percent can b calculated for certain progect after giving the progress percent for each activity

regards

Nilkamal Parikh
User offline. Last seen 1 year 21 weeks ago. Offline
Joined: 13 Jul 2009
Posts: 31

 

Hi Rafael,

I tried to create the S-Curve sample using the pdf file you have attached here. I did get everything exactly same until selecting Columns, Group & Sort & filter. But then after I don’t get that date options where I can select the time frame and time interval fields. I am straight away getting name he resource and finish. If I run that report it will only give me name of the resources but not the data as I can’t assign fields for this report. I am using P6 V7. Can you please tell me if there is anything different I need to do or any other way I can assign these two missing fields to my report to complete?

Thanks

Nilkamal

sudarshan singh
User offline. Last seen 5 years 16 weeks ago. Offline
Joined: 20 May 2011
Posts: 19
Groups: None

Hi Qasim,

If you updated civil construction then go with Physical progress %.

 

Sudarshan

Rafael Davila
User offline. Last seen 4 days 15 hours ago. Offline
Joined: 1 Mar 2004
Posts: 5241

I used Spider Project to demonstrate the use and interpretation of Cumulative or S Curves, the principles remain the same for all jobs no matter what software.

The S Curves are generated directly by Spider Project.

The risk charts are also from Spider Project, these are runs that represent true risk from the original schedule, not like with other software that import from a different software/version whose resource leveling and other functionalities such as use lag calendars, use of constraints and a few others are implemented differently, not all inconsistencies can be fixed by changing a few software options as some vendors will suggest.

I do not use P6 but using Google found the following links that shows a way to generate the data for creating S Curves.

http://primaverarena.com/wp-content/uploads/2010/05/S-curve-creation-for-P6.pdf

The following links provides some tutorials that might be of interest and perhaps showing a different approach.

http://www.toolboxforplanning.com/p/tutorials.html

http://www.toolboxforplanning.com/2010/10/excel-2003-tutorial-creating-progress-s_16.html

You can download their template or a modified version I just created to include early and late banana curves from the following link.

http://www.mediafire.com/download.php?ekc33bya2nd44e4

Good luck,

Rafael

Barry Fullarton
User offline. Last seen 11 years 17 weeks ago. Offline
Joined: 27 Aug 2008
Posts: 101
Groups: None

I see you are running the Graphs outside of P6 , in Risk Analysis? how did you manage to do this

 

Question

 

1. To set the baseline curve , i took the units as allocated in the resources , man-hours , and they were assigned at WBS Level , in a Level of Effort Activity ,

 

2. This was exported to Excel and we produced a Planned Curve, but this is the "early” start dates, need to know how to get the late Curve, so that I can form the ‘Californian” banana curve

3. We then track the Volumes done in a separate spread sheet that is aligned to the Activities in the Program,  

4. We get the summary Physical Percentage Complete from this and place this number into the Columns in P6 , now to calculate Performance Percentage Complete we reduce the Remaining Duration or extend it to ensure that Performance percentage and Physical match as closely as possible

5. once the above is done , we open the resource window at the bottom and ensure that the RD in the activity window equals the RD in the Resource

6. We then filter for the resources and “dump this out into excel and use the Actual to Date as Earned and the remaining as the Forecast

I am not sure how accurate this is as if your manipulate the RD in the resource tab , will it recalculate the Actual Hours , if so , its seem to be unstable in reporting  

Any Comments  

Barry Fullarton
User offline. Last seen 11 years 17 weeks ago. Offline
Joined: 27 Aug 2008
Posts: 101
Groups: None

I see you are running the Graphs outside of P6 , in Risk Analysis? how did you manage to do this

 

Question

 

1. To set the baseline curve , i took the units as allocated in the resources , man-hours , and they were assigned at WBS Level , in a Level of Effort Activity ,

 

2. This was exported to Excel and we produced a Planned Curve, but this is the "early” start dates, need to know how to get the late Curve, so that I can form the ‘Californian” banana curve

3. We then track the Volumes done in a separate spread sheet that is aligned to the Activities in the Program,  

4. We get the summary Physical Percentage Complete from this and place this number into the Columns in P6 , now to calculate Performance Percentage Complete we reduce the Remaining Duration or extend it to ensure that Performance percentage and Physical match as closely as possible

5. once the above is done , we open the resource window at the bottom and ensure that the RD in the activity window equals the RD in the Resource

6. We then filter for the resources and “dump this out into excel and use the Actual to Date as Earned and the remaining as the Forecast

I am not sure how accurate this is as if your manipulate the RD in the resource tab , will it recalculate the Actual Hours , if so , its seem to be unstable in reporting  

Any Comments  

Rafael Davila
User offline. Last seen 4 days 15 hours ago. Offline
Joined: 1 Mar 2004
Posts: 5241

S Curves can give you the information you are looking and more. Comparing difference between actual and baseline % at DD is very limited as you can see in the following figure. From the following figure, at DD [Data Date] costs [can be % Costs, %progress] fall between early and late values, it does not tells you about projected Overrun/Delay, these values are diaplayed for dates latter than actual DD.

S Curves

If you want more you shall look at the probabilities of success for Cost as well as for Project Finish. Do not count on these statistics be static.

Photobucket

Because the statistics are not static Success Probability Trends are needed to have a better view.

Photobucket

Qasim Alvi
User offline. Last seen 9 years 15 weeks ago. Offline
Joined: 13 Jan 2012
Posts: 4

Thanx Mike.

My concern is not about te dates but the progres percentages and not for activiteis but for overall project. For an example we say planned progress was 55% and actual is 50% with negative variance of -5%. So how to get that in P6.

Regards,

Qasim

Mike Testro
User offline. Last seen 12 weeks 3 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Qasim

You can show the original baseline underneath the progressed line or you can set up columns with both  sets of dates or you can do both.

Best regards

Mike Testro