Bringing whole schedule in by a month

1 reply [Last post]
S M
User offline. Last seen 2 years 24 weeks ago. Offline
Joined: 6 Oct 2012
Posts: 15
Groups: None

I have a schedule which the PM has asked for me to bring in by an entire month.

He wishes to know which items (which perhaps aren't critical now) would become critical if the whole delivery was brought in by a month.

I realise there a number of ways to do this (finish on/mandatory constraint, Filters etc.) but I was wondering what others or experienced PPs would do.

Thanks

Replies

Mike Testro
User offline. Last seen 22 weeks 6 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi S M

Assuming that the programme has been put together properly then the correct way to bring it in by one month is to:

1. Review the logic.

2. Increase resource levels on critical items - if workfront density allows.

3. Work overtime / weekends on critical items.

4. Check Non-Work days on the calendars.

Never do it by use of artificial constraints.

The first assumption will be your main problem because if the programme is already riddled with fundamental errors you will never get a realistic answer.

Best regards

Mike Testro