Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Transferring of Activity Progress

No replies
wilson reyes
User offline. Last seen 10 years 20 weeks ago. Offline
Joined: 23 Oct 2012
Posts: 3
Groups: None

Hi,

Im having problems on importing activity progress from my "Progress File" to my "Working File". I've tried doing the "P6 to Excel to P6" importing/exporting method. 

In the process of exporting my "Progress File" to excel, I called out "Activity % Complete" as part of my excel template. Then, it reflected as "(*) Activty % Complete (%)" on the excel spreadsheet. it was mentioned in the forums changes made on those with asterrisks (*) will not be reflected once imported back to P6.

Can you guys suggest any method/s on how to work around this?

THANK YOU VERY MUCH!

btw, I'm using P6 V6.0