MSP resource tracking problem, help needed.

Member for

13 years 2 months
Permalink

Thank you for your reply Alex,I will try this!/Bogdan

Member for

13 years 2 months
Permalink

Thank you for your reply Alex,I will try this!/Bogdan

Member for

22 years 9 months
Permalink

Bogdan,Have a look at Resource Usage; you will read that the resource has worked 1h/day to consume 32 hours in 32 days. Because the initial 32 hours are actual work, MSP will not change them, it will instead schedule the additional 100 hours from day 33 with a rate of 8 hours/day.The Task type field on your task says "Fixed Duration", therefore MSP cannot freely change the scheduled duration of the task, and it will display the scheduling message advising the new duration.The easiest way to do is:remove the resource from the task, and click OKassign the ressource again, enter 132 in the Work column, 32 in the Actual Work, and click OKthe resource has been working long enough to achieve the 1st 32 hours.Alexandre